A foreign investor who wants to run a hotel must choose between leasing an existing building and building a new hotel. This article sets out the order of procedures for each model and the licences specific to hotels.
About this article
A foreign investor going into the hotel business needs to choose first between leasing an existing building and building a new hotel, because the two models follow a different order of procedures.
This article provides general information and does not replace legal advice for a specific case.
For a foreign investor going into the hotel business, the order between setting up the company, leasing a building or securing land, and obtaining the Investment Registration Certificate affects three points:
- when the hotel can start receiving guests;
- when the investor starts paying rent for the building or paying for the land;
- when the company can handle work permit and residence procedures for foreign staff.
The right option depends on the investment model. An investor leasing an existing building can follow a sequence close to that of a restaurant project. An investor building a new hotel must also deal with land, construction, environmental and fire safety procedures. This article sets out the options for proceeding, the three capital thresholds, the requirements for the building or the land, and the licences specific to hotels.
Under the 2025 Investment Law, a foreign investor may set up the company first and then complete the procedure for the Investment Registration Certificate within 12 months from the date of establishment. Before the company has this certificate, it may not implement the project and may not add business lines. The sequence for a restaurant project is analysed in Opening a restaurant in Vietnam: in what order should a foreign investor proceed.
1. The investor chooses an option according to whether it leases a building or builds a new hotel
When leasing an existing building, the investor can choose one of the first four options below. When building a new hotel, the investor follows the option in section 1.5.
1.1. Option 1: set up the company before finding a building
The investor takes the following steps:
- Set up the company at an office address, registering the accommodation services line from the start.
- Find a building and sign the lease.
- Apply for the Investment Registration Certificate for the hotel in that building.
The advantage of this option is that the company exists as a legal entity early. The company can open accounts and prepare procedures for foreign staff, while the investor does not yet pay rent for the building.
The disadvantage is that the company cannot operate until it has the Investment Registration Certificate. The investor must also find a building and complete the procedure within 12 months from the date the company is set up.
1.2. Option 2: lease the building, then set up the company
The investor takes the following steps:
- Lease the building. As the company does not yet exist, the investor signs the lease and should agree in advance with the landlord that the lease will be transferred to the company.
- Set up the company with its address in that building.
- Apply for the Investment Registration Certificate for the hotel.
The advantage of this option is that the company's head office and the hotel location are fixed from the start. The company applies for the Investment Registration Certificate only once and does not need the amendment required under the recommended option.
The disadvantage is that the investor pays rent for the whole waiting period. For a hotel, the rent for a whole building is usually much higher than the rent for restaurant premises. The investor also bears the risk that the project in that building is not granted an Investment Registration Certificate.
1.3. Option 3: obtain the Investment Registration Certificate first
The investor takes the following steps:
- Lease the building.
- Apply for the Investment Registration Certificate for the hotel in that building.
- Set up the company.
The advantage of this option is that the investment registration authority reviews the project file for the building before the investor sets up the company. The project file must state the address, the area and the conformity with planning, and the investment registration authority reviews the file on that basis.
The disadvantage is that the company is set up later. Work permit and visa procedures for foreign staff therefore also start later than under the other options.
1.4. The option we recommend when leasing a building
The investor takes the following steps:
- Set up the company with the accommodation services line and other intended lines, such as consulting.
- Obtain the Investment Registration Certificate for the other lines so that the company can operate at once.
- Find a building and sign the lease.
- Amend the Investment Registration Certificate to add capital and the hotel activity in that building.
The advantage of this option is that the company can operate early. The company obtains the Investment Registration Certificate within the 12-month period even before a building is found. The investor has time to find a building while transferring capital and obtaining a visa and work permit.
The disadvantage is that the company makes one more amendment to the Investment Registration Certificate and bears the related cost.
Under this option, the company must register the accommodation services line when it is set up. The reason is that the company may not add business lines before it has the Investment Registration Certificate. If this line is missing at the start, the company can add it only after the certificate is issued.
1.5. Option for building a new hotel
The investor takes the following steps:
- Decide how to secure the land: sublease land with infrastructure in a zone, acquire land use rights, or ask the State to allocate or lease land.
- Obtain an investment policy approval if the project requires one.
- Obtain the Investment Registration Certificate, then set up the company.
- Complete the environmental procedure, the fire safety design appraisal where required, and the construction permit.
- Build, carry out acceptance, and complete the accommodation business procedures in section 4 before receiving guests.
The advantage of this option is that the investor controls the scale, design and class of the hotel. The investor does not depend on the lease term offered by a building owner.
The disadvantage is that the time from securing the land to receiving guests is much longer, and the investor has more procedures to complete. The time needed for policy approval and land procedures is hard to predict and may exceed 12 months. For a new hotel, the investor should therefore obtain the Investment Registration Certificate first and set up the company afterwards. The cases that require policy approval are analysed in When a project needs investment policy approval.
Under every option that involves leasing a building, when signing the lease, the investor should negotiate a right to terminate it if the hotel activity in that building is not approved.
2. The investor should plan the initial capital around three thresholds
| Threshold | Content | Consequence |
|---|---|---|
| 90 days | The owner, members or shareholders contribute the full charter capital from the date of the Enterprise Registration Certificate | If the capital is not fully contributed, the company must register a change of charter capital to the amount actually contributed within 30 days from the last day of the contribution period |
| 12 months | The company completes the procedure for the Investment Registration Certificate from the date of establishment | This period does not extend the 90-day contribution period |
| VND 3 billion | Capital contributed by an individual investor | From VND 3 billion, the owner or a member of a limited liability company, and the Chairman or a member of the Board of Directors of a joint stock company, are not subject to a work permit. An investor contributing from VND 3 billion to under VND 50 billion may obtain a DT3 temporary residence card for up to 03 years. Below VND 3 billion, an investor working for the company needs a work permit. The investor cannot obtain a temporary residence card as an investor, but may obtain one as an employee after the work permit is issued |
An individual investor should therefore take residence needs into account when choosing the initial capital. The investor should also set the charter capital at an amount it can transfer within 90 days. For a new hotel, the project's investment capital is usually much higher than the charter capital. The difference may be loans or other raised funds, recorded in the schedule for contributing and raising capital in the Investment Registration Certificate.
From 05/12/2026, work permit procedures follow Decree 393/2026/ND-CP. Applications filed before that date still follow Decree 219/2025/ND-CP.
The company may open a direct investment capital account before it has the Investment Registration Certificate. During this period, the company may use the account only to receive capital contributions, receive deposit interest, pay lawful pre-investment costs, and return the capital if the certificate is not issued.
3. The investor should appraise the building or the land before signing
3.1. When leasing an existing building
The investor should check the following points before signing the lease:
- Type of building. An apartment in an apartment building may not be used for any purpose other than housing. Service areas in a mixed-use apartment building may change their use only with permission from the competent authority.
- Location of the building. An investment project requires an investment policy approval, regardless of its size, when the location is in protection zone I or II of a national relic, a special national relic or a relic on the World Heritage List, or in the restricted development area or historic inner city of a special-class city such as Hanoi or Ho Chi Minh City. The rule does not exclude the case where the investor only leases an existing building. The investor should check the planning at the building before signing the lease.
- Minimum number of rooms. A hotel must have at least 10 bedrooms, a reception desk and shared toilets, together with the other minimum conditions in section 4.
- Construction permit. Repair and renovation inside a building are exempt from a construction permit when they do not change the purpose, function or load-bearing structure of the building. If the investor renovates an office building or a house to use it as a hotel, the renovation changes the function of use, so it does not fall within this exemption.
- Fire prevention and fighting. A hotel must meet the fire safety conditions before it starts operating. A hotel that reaches the threshold for number of floors or floor area on the list of works requiring fire safety design appraisal must have its design appraised when it is built or renovated. The investor should identify this threshold with the design consultant before signing the lease. For such a hotel, the project owner organises the fire acceptance check itself and declares it on the fire prevention and fighting database before the hotel starts operating.
- Parking. The minimum conditions for hotels require parking for guests only for resort hotels and roadside hotels. Parking requirements for city hotels may arise from local planning standards when a building is constructed or renovated.
3.2. When building a new hotel
The investor should check the following points before signing a land agreement:
- Investment policy approval. The project requires a policy approval when the investor asks the State to allocate or lease land without an auction or tender, or asks for a change of land use purpose, except in certain cases excluded by law. The project also requires one when the land is in the areas described in section 3.1, is in an area affecting national defence or security, or when the project includes betting or casino business. A project that subleases land with infrastructure from the developer of a zone usually does not require a policy approval on land grounds.
- Deposit. If the State allocates or leases land or permits a change of land use purpose, the investor must post a deposit or a bank guarantee of the deposit obligation, except in certain cases such as winning a land auction or tender.
- Construction permit. A new hotel needs a construction permit, except in certain cases, such as works in a project under the special investment procedure, or a project whose feasibility study report has been appraised by the specialised construction agency. In the exempt cases, the project owner must still send a commencement notice.
- Environment. Depending on its scale and location, the project must prepare an environmental impact assessment report, obtain an environmental permit, or make an environmental registration. The investor should identify the project's group under the environmental protection law when preparing the project proposal.
- Fire prevention and fighting. A hotel subject to fire safety design appraisal under section 3.1 must have its design appraised before construction starts.
4. A hotel needs some specific licences and procedures
Besides the investment procedure, the company should note the following licences and obligations:
- Market access. The investor should check the market access conditions for accommodation services before submitting the project file. Under Vietnam's WTO accession commitments, hotel lodging services are no longer restricted for the commercial presence of foreign investors after 8 years from accession. The investor should still check the specific conditions on the National Investment Information Portal and in the treaty that applies to its nationality.
- Conditions for tourist accommodation services. The company must be registered for business; meet the conditions on security and order, fire safety, environmental protection and food safety; and meet the minimum conditions on facilities and services. For a hotel, the minimum conditions include electricity, water supply and drainage; at least 10 bedrooms; staff on duty 24 hours a day; and a manager and staff trained in tourism skills.
- Notice before operation. At least 15 days before starting operation, the company sends a written notice to the provincial tourism authority. The notice states the name, type, scale and address of the hotel, the legal representative and a commitment that the business conditions are met. The authority then checks the minimum conditions of the hotel. When the name, scale, address or legal representative changes, the company must notify again.
- Star rating. Rating is voluntary. The company may use the word "star" or a star image in advertising only after the competent authority recognises the rating. The central tourism authority recognises 04-star and 05-star ratings; the provincial tourism authority recognises 01 to 03-star ratings. A rating decision is valid for 05 years.
- Certificate of eligibility for security and order. Accommodation services are a business line that must hold this certificate before operating. The authority that issues the certificate depends on the size of the facility. The company should ask the provincial police where the hotel is located about where to file. The hotel must check guests' identity documents; if a guest has none, the hotel must immediately inform the commune police or the police station in charge of the area.
- Temporary residence declaration for foreign guests. The hotel declares the temporary residence of foreign guests to the police where the hotel is located within 12 hours, or 24 hours in remote areas, from the guest's arrival.
- Restaurant in the hotel. A restaurant in a hotel does not need a food safety certificate, but must still meet the food safety conditions.
- Business Licence. Accommodation services are not among the nine groups of activities that require a Business Licence. In our view, a company that only provides accommodation does not need this licence. If the hotel has a shop selling goods to guests, the company should review the position, because this activity may be retail of goods.
- Alcohol and tobacco. While Resolution 66.18/2026/NQ-CP applies, until the end of 28/02/2027, the company does not have to meet the business conditions for alcohol, including when it sells alcohol for on-site consumption, and does not need a tobacco retail licence. Guidance is not consistent on whether the company must still register the sale of alcohol for on-site consumption. The company should ask the commune People's Committee where the hotel is located before selling alcohol.
- Music royalties. A company that plays music for guests in the lobby, the restaurant or the hotel rooms must pay royalties to the right holders. A personal music subscription does not include the right to play music in a business.
- Signboard. The signboard must show in Vietnamese the name of the business as registered, the address and the telephone number. Any foreign text must be placed below and may not be larger than three quarters of the Vietnamese text. Trademarks and internationalised foreign proper names do not have to be translated.
5. What to avoid when opening a hotel
- Signing a long lease before appraising the building. The investor should first check the type of building, the number of rooms, the construction permit for the renovation and fire safety, and then include a termination clause in the lease.
- Setting up the company without the accommodation services line. The company cannot add this line before it has the Investment Registration Certificate.
- Setting up the company before settling the land procedure for a new hotel. Policy approval and land procedures may take longer than 12 months.
- Setting the charter capital without considering residence needs. If the contribution is below VND 3 billion, an individual investor working for the company needs a work permit and cannot obtain a temporary residence card as an investor.
- Receiving guests before sending the notice and before obtaining the certificate of eligibility for security and order. The company should receive guests only after completing these procedures and meeting the fire safety conditions.
- Advertising a star rating before it is recognised. The company should use the word "star" only after it has a rating decision.
6. Conclusion
When leasing an existing building, a foreign investor can set up the company first, register the accommodation services line from the start and plan the initial capital around the three thresholds of 90 days, 12 months and VND 3 billion. When building a new hotel, the investor should first settle the land procedure and any policy approval, and obtain the Investment Registration Certificate before setting up the company.
Before receiving guests, the company must meet the conditions for tourist accommodation services, send the notice to the provincial tourism authority, hold the certificate of eligibility for security and order, and meet the fire safety conditions.
Tin & Partners can work with investors to choose how to proceed, appraise the building or the land, and prepare the files before submission.
Read more on setting up an FDI company
- Related: Opening a restaurant in Vietnam: in what order should a foreign investor proceed
- Related: When a project needs investment policy approval
- Related: Company first or investment certificate first
- Related: Choosing the charter capital of a foreign invested company
This article is based on Investment Law No. 143/2025/QH15, the Enterprise Law, Tourism Law No. 09/2017/QH14, Construction Law No. 135/2025/QH15, Decree 96/2026/ND-CP, Decree 168/2017/ND-CP, Decree 96/2016/ND-CP as amended by Decree 392/2026/ND-CP, Decree 105/2025/ND-CP, Resolution 66.18/2026/NQ-CP, the laws on entry and residence of foreigners and on environmental protection, and instruments issued up to November 2026. It is for general information only and does not replace legal advice on a specific case.